2023
May-August:
- Trench and backfill completed
- Electrical duct bank installation completed
- Asphalt patching
January:
- All project structural foundations have been completed
- The fist-floor reinforced concrete slab has been completed
- Rebar installation on 2nd-floor slab and next concrete pour
2022
September:
- Shear walls and column placements completed
- Graphic sound wall mural installed
August:
- Vertical formwork structure started
May:
- May 13: Groundbreaking