Construction Milestones

2023

May-August:

  • Trench and backfill completed
  • Electrical duct bank installation completed
  • Asphalt patching

January:

  • All project structural foundations have been completed
  • The fist-floor reinforced concrete slab has been completed
  • Rebar installation on 2nd-floor slab and next concrete pour

2022

September:

  • Shear walls and column placements completed
  • Graphic sound wall mural installed

August:

  • Vertical formwork structure started

May:

  • May 13: Groundbreaking